"Lean shipping: Better all the time"

Lean principles apply to every type of organization, not just manufacturing. Using effective process improvement methods, the Peters Company helped Robinson Nursery create better lean shipping in their operation.

Robinson Nursery is a grower of Bareroot Shade/Ornamental Trees and Shrubs. The Peters Company is sharing this case study published in the nursery's October 2018 newsletter.

Better all the time
“In September, we had the opportunity to partner with The Peters Company and perform a Lean kaizen event in our container yard. Our specific focus was the process of pulling and preparing trees for shipping.

Our innovative group of problem solvers included those who have been a part of the plant pulling process for years. Key team members, supervisors, managers, and office staff helped dissect the process, identify issues and create a better system. Everyone was eager to jump in looking for ways to eliminate waste, add value, and eradicate inconsistency.

If you have been following the Lean transformation of Robinson Nursery it is likely you have become familiar with the formula for improving a process. The journey of a plant was mapped; from being pulled out of production to being loaded on the shipping truck. The steps that added value to the product were identified and we began looking for ways to eliminate the rest. The team discovered that much of their frustration came from batch processing, poor communication, and unclear standard work.

Netting machines are now moved to the bed where the plants are pulled. One piece flow eliminates wasted motion, traffic jams, and over processing. The logistics of the new process were thoroughly mapped out and standard work was created to properly train the rest of the crew. This guarantees fewer defects and significantly boosts consistency.

Three days were dedicated to this event. Prior to this event, it took three days to process a full truck order, about 3200 trees. That same order can now be done in about a day and a half with greater accuracy and less strain on the team.”

Lean Shipping: Value to Robinson Nursery

  • Standard work developed
  • Cut lead time in half
  • More than 30% fewer product touches
  • Crew size reduced from 11 to 6
  • Engaged and motivated employees

"The numbers are exciting but what is even more gratifying is the new attitude in that division of our company. The time and opportunity that was given to share ideas and trial different methods was a truly empowering and meaningful bonding experience for everyone involved. We are grateful to the Peters Company for taking the time to help us create a better tomorrow."

For more information:
petersco.net
www.robinsonnursery.com